The construction of a district community centre in Brabham which includes function halls, meeting rooms, food preparation areas, storerooms and an external function area.
Project status
- This project is on hold as per Council decision dated December 14, 2022.
Project timeline
Concept design
Completed July 2022
Community consultation
Completed October 2022
Detailed design
In progress 2023/24
Construction start
Scheduled in 2025/26
Construction finish
Expected in 2026/27
FAQ's
We've had to delay timing of construction because of the high costs in the market right now. Proceeding at this time would compromise our ability to meet the important needs for our community. So, we're waiting for better conditions to ensure we can deliver all the elements in which the community requires.